Project overview*
| EIS status | Approved with conditions |
| Description | Open-cut coal mine with a yield of up to 10 million tonnes per annum. |
| Proponent | Byerwen Coal Pty Ltd (joint venture between QCoal Pty Ltd and JFE Steel) |
| Location/s | Northern Bowen Basin, 20 km west of Glenden and 140 km west of Mackay. Map |
| Local government/s |
|
| Investment | $1.76 billion |
| Key features |
|
| Jobs |
|
* Project information supplied by proponent and subject to change.
Environmental impact statement (EIS) process
| Date | Activity |
|---|---|
| 2 October 2014 | Commonwealth Minister for the Environment's approval of 'controlled action', subject to conditions.
|
| 2 July 2014 | Coordinator-General's Report for the Byerwen Coal project ( |
| 29 January 2014 to 25 February 2014 |
Additional information for the EIS and submissions being assessed by other government agencies. |
| 16 September 2013 | Additional information for the EIS requested by Coordinator-General. |
| 8 June 2013 to 23 July 2013 |
Draft EIS public consultation
|
| 19 July 2011 | Terms of reference for EIS ( |
| 9 April 2011 to 16 May 2011 |
Draft terms of reference for EIS public consultation. |
|
1 March 2011 |
Gazettal of 'coordinated project' declaration ( |
|
4 February 2011 |
Application, including initial advice statement ( |
| 13 January 2011 | Project deemed a 'controlled action' by Commonwealth Minister for the Environment. |
| 14 December 2010 | Project referred to Commonwealth Minister for the Environment. |
Read more about the EIS process.
Project changes
Project change application – Relocation of Southern Infrastructure
| Date | Activity |
|---|---|
| 3 July 2015 | Coordinator-General's report on project change ( |
| 2 June 2015 | Proponent's project change application submitted ( |
Annual report to the Coordinator-General
The proponent is required to submit an annual report to the Coordinator-General.
Further information
For more information, visit the Byerwen Coal project web page.