Project overview*

EIS status EIS active
Description 224 km single-track dual-gauge freight railway
Proponent Australian Rail Track Corporation Limited
Location/s Queensland Border to Gowrie. Map
Local government/s
  • Goondiwindi Regional Council
  • Toowoomba Regional Council
Investment $1.4 billion
Key features
  • 146 kilometres of new dual-gauge track and 78 kilometres of upgraded track to accommodate double stack freight trains up to 1800 metres long
  • construction of rail infrastructure, bridges, viaducts and crossing loops
  • connection to the existing West Moreton System and Interstate railway lines
  • ancillary works including road and public utility crossings and realignments.
Expected completion 2024
Jobs
  • 1600 (construction)
  • TBA (operational)

Environmental impact statement (EIS) process

Date Activity
Currently Draft terms of reference for EIS being prepared.
9 April 2018 Delegate for the Commonwealth Minister for the Environment and Energy decided that the project is a 'controlled action.'More information
16 March 2018 Gazettal (PDF icon 251 KB) of 'coordinated project' declaration.
2 March 2018 Complete final initial advice statement (PDF icon 19 MB), submitted

The above has also been split into smaller documents for easier downloading:

Final initial advice statement part 1 of 5 (PDF icon 4.4 MB), submitted
Final initial advice statement part 2 of 5 (PDF icon 4.9 MB), submitted
Final initial advice statement part 3 of 5 (PDF icon 4.9 MB), submitted
Final initial advice statement part 4 of 5 (PDF icon 4.6 MB), submitted
Final initial advice statement part 5 of 5 (PDF icon 1 MB), submitted
16 February 2018 Application, including initial advice statement submitted.
16 February 2018 Project referred to Commonwealth Minister for the Environment and Energy.

Further information

Read more about the EIS process.