Project overview*

EIS status EIS active
Description 47 kilometre single-track dual-gauge freight railway
Proponent Australian Rail Track Corporation Limited
Location/s Helidon to Calvert through the Little Liverpool Range. Map
Local government/s
  • Ipswich City Council
  • Lockyer Valley Regional Council
Investment $1 billion
Key features
  • 47 kilometre single-track dual-gauge freight rail line to accommodate double stack freight trains up to 1800 metres long
  • a 1.1 kilometre tunnel through the Little Liverpool Range
  • construction of rail infrastructure, culverts, bridges, viaducts and crossing loops
  • connection to the existing West Moreton Railway Line
  • ancillary works including road and public utility crossings and realignments
Expected completion 2024
Jobs
  • 1800 (construction)
  • TBA (operational)

* Project information supplied by proponent and subject to change.

Have your say

The Coordinator-General has prepared draft terms of reference (TOR) for an environmental impact statement (EIS) for the Inland Rail – Helidon to Calvert project.

The draft TOR sets out the matters the project proponent, Australian Rail Track Corporation Limited (ARTC) must address when preparing the EIS.

The public comment period on the draft TOR was previously open between 6 May 2017 and 5 pm, 5 June 2017.

The Coordinator-General has decided to extend the public notification period until 5 pm, 26 June 2017 to allow further opportunity to comment on the draft TOR.

Comments received during the comment period will be considered by the Coordinator-General in finalising the TOR.

You are invited to comment on whether the draft TOR adequately covers all the matters ARTC must address when preparing the EIS.

The Coordinator-General will consider your comments before finalising the TOR.

Comments close at 5.00 pm 26 June 2017.

Read and comment on the draft TOR.

Environmental impact statement (EIS) process

Date Activity
6 May 2017 to 26 June 2017 Draft terms of reference for EIS public consultation (PDF icon 283 KB).
17 March 2017 The delegate for the Commonwealth Minister for the Environment and Energy decided the project is a 'controlled action'. More information
16 March 2017 Gazettal (PDF icon 240 KB) of ‘coordinated project’ declaration.
15 February 2017 Application, including initial advice statement (PDF icon 22.4 MB), submitted.
10 February 2017 Project referred to Commonwealth Minister for the Environment and Energy.

Media releases

Further information

Read more about the EIS process.