Project overview*
| EIS status | Approved with conditions |
| Description | Liquefied natural gas plant - staged construction of up to four trains producing up to 18 million tonnes per annum of LNG. |
| Proponent | Arrow CSG (Australia) Pty Ltd (formerly Shell CSG (Australia) Pty Ltd) |
| Location/s |
|
| Local government/s | Gladstone Regional Council |
| Investment | $15 billion |
| Key features |
|
| Jobs |
|
* Project information supplied by proponent and subject to change.
Environmental impact statement (EIS) process
| Date | Activity |
|---|---|
| 10 December 2013 | Commonwealth Minister for the Environment's approval of 'controlled action', subject to conditions.
|
| 10 September 2013 | Coordinator-General's report on EIS ( |
| 8 February 2013 to 8 March 2013 |
Additional information to EIS assessed by other government agencies. |
| 31 July 2012 | Request by Coordinator-General for proponent to provide additional information to EIS. |
| 14 April 2012 to 28 May 2012 |
EIS public consultation. |
| 22 January 2010 | Terms of reference for EIS ( |
| 3 October 2009 to 2 November 2009 |
Draft terms of reference for EIS public consultation. |
| 21 August 2009 | Project deemed a 'controlled action' by Commonwealth Minister for the Environment.
|
| 21 July 2009 | Project referred to Commonwealth Minister for the Environment. |
| 12 June 2009 | Gazettal of 'coordinated project' declaration ( |
| 11 May 2009 | Application, including initial advice statement, submitted.
|
Read more about the EIS process.
Media releases
$15b Arrow LNG project given approval (10 September 2013)