Since the publication of the Coordinator-General's report on the EIS, the proponent has applied for the following changes to the Cross River Rail project.
Project change application 5– Condition change (hours of work) 2019
| Date | Activity |
|---|---|
| 4 October 2019 | Coordinator-General's report on project change ( |
| 3 October 2019 | The Coordinator-General decided not to publicly notify the proponent’s change application. |
| 23 September 2019 | Proponent’s change application submitted ( |
Project change application 4 – Whole of project refinements 2019
Project change application 3 – Roma Street demolition works
| Date | Activity |
|---|---|
| 14 March 2019 | Coordinator-General's report on project change ( |
| 4 March 2019 | Proponent submitted revised information: Roma Street demolition works updated traffic assessment technical note ( |
| 1 December 2018 to 21 December 2018 | Public consultation of project change application.
|
| 19 November 2018 | Proponent's change application submitted. |
Project change application 2 – Temporary Roma Street Coach Terminal
| Date | Activity |
|---|---|
| 31 August 2018 | Coordinator-General's report on project change ( |
| 23 August 2018 | Proponent submitted revised information: |
| 3 August 2018 | Proponent submitted revised information: |
| 17 July 2018 | The Coordinator-General decided not to publicly notify the proponent's change application. |
| 28 June 2018 | Proponent's change application submitted: |