Project overview*
| EIS status | EIS active |
| Description | A 1,100-kilometre high-voltage overhead electricity transmission line connecting the North West Minerals Provence and Mount Isa to the National Electricity Market grid south of Townsville. |
| Proponent | CuString Pty Ltd |
| Location/s | The transmission line would run from a new sub-station at Woodstock, south of Townsville, to the Chumvale sub-station, near Cloncurry. Subject to demand, the line may extend west to Mount Isa and south to existing and potential mining operations. View map. |
| Local government/s |
|
| Investment | $1.5 billion |
| Key features |
|
| Expected completion | 2024 |
| Jobs |
|
* Project information supplied by proponent and subject to change.
Environmental impact statement (EIS) process
| Date | Activity |
|---|---|
| Currently | Draft EIS being prepared by proponent. |
| 4 September 2019 | Terms of reference for an EIS ( |
| 8 July to 2 August 2019 | Draft terms of reference ( |
| 14 May 2019 | Delegate for the Commonwealth Minister for the Environment decided that the project is a 'controlled action' |
| 26 April 2019 | Gazettal of 'coordinated project' declaration ( |
| February 2019 | Initial advice statement submitted ( |