Since the publication of the Coordinator-General's report on the EIS, RTA Weipa Pty Ltd has applied for the following changes to the South of the Embley (Amrun) project.

Project change application 4 – Accommodation term and location

Date Activity
3 November 2015 Coordinator-General's report on project change (PDF icon 197.0 MB) released, approving the change.
14 October 2015 to
28 October 2015
Project change application (PDF icon 8.8 MB) public consultation.
28 September 2015 Proponent's project change application submitted.

Project change application 3 – Infrastructure facilities and volume and disposal of dredge spoil

Date Activity
18 September 2015 Coordinator-General's report on project change (PDF icon 193 KB) released, approving the change.
15 September 2015 Proponent's project change application (PDF icon 157 KB) submitted.

Project change application 2 – General conditions

Date Activity
21 November 2013 Coordinator-General's report on project change (PDF icon 813 KB) released, approving the change.
30 August 2013 Proponent's project change application (PDF icon 4.85 MB) submitted.

Project change application 1 - Social conditions

Date Activity
1 October 2013 Coordinator-General's report on project change (PDF icon 591 KB) released, approving the change.
30 August 2013 Proponent's project change application (PDF icon 4.1 MB) submitted.

Read more about project changes.