Project overview*
| EIS status | Approved with conditions |
| Description | A road network, including underground toll road and elevated structures, to connect Brisbane's northern arterials of Gympie Road at Kedron and Sandgate Road and the east-west arterial at Toombul, to the Inner City Bypass and North - South Bypass Tunnel at Bowen Hills. |
| Proponent | The State of Queensland. The State contracted BrisConnections to finance, design, construct, commission, operate and maintain Airport Link for 45 years. State-owned City North Infrastructure Pty Ltd provides management services related to the agreement between the State and BrisConnections. |
| Location/s | Brisbane (Bowen Hills-Clayfield) (6.7 km). Map |
| Local government/s | Brisbane City Council |
| Key features |
|
* Project information supplied by proponent and subject to change.
Queensland Ombudsman's investigation
In August 2010, following a complaint from nearby residents, the Queensland Ombudsman commenced an investigation into noise from night-time surface works on the Airport Link Project.
Residents complained that the noise of night-time surface works, some of which was occurring 24/7, was unlawful.
Following the investigation, the Ombudsman released his report in June 2011.
The Ombudsman found that night-time surface works are allowed under the conditions set for the project - as long as those works do not generate excessive noise, vibration, dust and traffic.
He found that the meaning of 'excessive noise' was not defined in project documents, which hindered the effective regulation of noise from night-time surface works.
The Ombudsman made 24 recommendations about improving the regulation and monitoring of noise from night-time surface works.
The Queensland Ombudsman asked the Coordinator-General to notify him of steps taken, or proposed to be taken, to give effect to the Ombudsman's recommendations.
The recommendations generally comprise:
- actions to better define noise regulation terms
- actions to better determine what works being conducted at night fall outside of the 'special circumstances' provisions and more effectively regulate noise generated by those night-time construction activities.
The Coordinator-General has responded to the Ombudsman, committing to take the necessary steps to implement all the recommendations relating to the Office of the Coordinator-General.
Download response
Response of the Coordinator-General to the Queensland Ombudsman (
454 KB)
In May 2007, after evaluating the project proponent's environmental impact statement (EIS), the Coordinator-General released a report recommending the project proceed subject to conditions.
The conditions relevant to the Queensland Ombudsman's investigation are:
- Condition 7 (b) - which establishes the days and hours surface works are allowed, including works that generate 'excessive levels of noise'.
- Condition 9 (d) - which sets out noise goals, the exceedance of which triggers the implementation of mitigation measures and monitoring.
Download report
For more details, read the Coordinator-General's report on the EIS - Appendix 1 - Conditions (
635 KB).
In May 2010 - prior to the complaints that triggered the Ombudsman's investigation - the Coordinator-General clarified and reinforced the term 'excessive noise'.
However, in response to recommendation 12 of the Ombudsman's report, the Coordinator-General decided to amend the May 2010 clarification and reinforcement of the term 'excessive noise'.
Following is an excerpt of a letter sent to BrisConnections (the concessionaire) and Thiess John Holland (the builder) on 3 February 2012, detailing the amendment:
Definition of the term 'excessive noise'
The generation of excessive noise, as stated in Condition 7, occurs when noise measured at a sensitive place (for example inside of a bedroom of a home nearby) exceeds the noise goals stated in the Coordinator-General's Report, Appendix 1, Schedule 3, Condition 9, or the background noise (whichever is greater).
Internal noise goals for sleeping areas have been set for the project during night hours (from 6.30 pm to 6.30 am). These noise goals are based on existing national standards for sleep disturbance. The goals are detailed [in] Appendix 1, Schedule 3, Condition 9 (d) (i) and (ii).
Measurement of noise at night
The noise goals [in] Condition 9 (d) are based on noise measured internally, in the sleeping areas of a residence.
In a residence that has had noise mitigation applied to the sleeping areas, monitoring is to be undertaken with the mitigation active. However, in a residence that has not had noise mitigation applied to the sleeping area, monitoring is to be undertaken with the sleeping area in the state in which it is normally occupied.
For example, this may mean that if the state in which the sleeping area without mitigation applied is normally occupied includes windows open to a certain extent, then noise monitoring is to be conducted with the windows open to this extent.
Thiess John Holland advised a former Coordinator-General of difficulty in measuring noise inside homes for which noise complaints have been made. It is understandable that residents are reluctant to allow strangers in their homes during the night.
I support the former Coordinator-General's advice to Thiess John Holland that a suitable alternative method is to measure the noise levels externally and deduct an amount of 10 dB ('A' weight scale) to obtain an approximate internal value. These measurements should be conducted in accordance with the Department of Environment and Resource Management's Noise Measurement Manual.
Enforcement of breach of Condition 7 (b) - 'excessive noise'
Prior to determining whether to commence enforcement action for a breach of Condition 7 (b), factors that I may consider include:
- whether the works carried out are construction activities other than spoil haulage works
- whether the works occurred outside the hours of 6.30 am to 6.30 pm, Monday to Saturday
- what levels of noise were generated by the works
- whether there were special circumstances justifying those works outside those hours
- whether those levels are excessive.
To establish that those noise levels that are exceeding the Condition 9 (d) levels are excessive, factors that I may consider are the:
- duration, number and time of those exceedences
- level of those exceedences
- effect of those exceedences
- mitigation provided and/or offered
- consultation conducted.
When considering the effect of noise exceedences, I may:
- seek evidence from persons affected by the noise
- seek expert advice to explain the significance of any level of exceedence.
The consideration of whether the noise was excessive noise under Condition 7(b) and whether to take enforcement action may also involve taking into account the actions of BrisConnections, Thiess John Holland and the resident in relation to mitigation of the residence. Where noise modelling predicts that noise goals for sleep disturbance are likely to be exceeded by construction works, then reasonable and practicable mitigation and management measures must be adopted. The measures taken in such circumstances would be part of any assessment of whether noise has been excessive.
Consideration must be given to circumstances where a property owner and/or resident refuses mitigation measures offered. In these circumstances, the review will consider the application of a 'reasonable and practical' test to the resident, BrisConnections and Thiess John Holland. The Coordinator-General also will be guided by the Strategic Compliance Plan when considering whether to undertake enforcement action.
In response to recommendation 5 of the Queensland Ombudsman's report, the Coordinator-General has published the following statement, clarifying the meaning of the terms 'temporary' and 'long term' for steady construction noise under Condition 9 (d):
With reference to the terms 'temporary' and 'long term' steady construction noise contained within Appendix 1, Schedule 3, Condition 9 (d) of the Coordinator-General's Report for the Airport Link Project, having considered the information presented in the Ombudsman's Airport Link Project Report 2011, and other noise impact advice and assessment, I am of the view that, given the long construction period for this project (approximately 4 years), the construction noise generated by the project is long-term noise.
In particular, the temporary noise goals are only appropriate for one-off operations that last for one night only, for example the mobilisation or demobilisation of a Favco tower crane. I consider that for any other steady construction noise, the long-term noise goals should be applied.
It is my expectation that for the remainder of the construction phase of the Airport Link Project, construction noise impacts will be assessed, monitored, mitigated and managed in accordance with this interpretation of how the 'temporary' and 'long term' noise goals should be applied for the purposes of Appendix 1, Schedule 3, Condition 9 (d).
It follows that this interpretation also applies when assessing what is 'excessive noise' in accordance with the previous clarification and reinforcement of the term 'excessive noise' in Appendix 1, Schedule 3, Condition 7 (b).
In response to recommendation 21 of the Queensland Ombudsman's report, the Coordinator-General has published a targeted noise monitoring program (
34 KB) for the Airport Link Project.
In response to recommendation 6 of the Queensland Ombudsman's report, the Coordinator-General has defined 'major roads' and 'minor roads' in Brisbane as follows:
- major roads - those shown in Map D of the Brisbane City Council's City Plan 2000
- minor roads - those not shown in the abovementioned map.
These terms appear in Table 3 of Condition 9, Schedule 3, Appendix 1 of the Coordinator-General's Change Report on the Airport Link Project, July 2008.
Environmental impact statement (EIS) process
The proponent prepared an EIS for the Airport Link Project in accordance with the terms of reference for an EIS:
| Date | Activity |
|---|---|
| 23 May 2007 | Coordinator-General's report on EIS (
|
| 12 April 2007 | Supplementary EIS (
|
| 11 October 2006 | Environmental impact statement Also available at the State Library of Queensland (record number: 775127) |
| 1 March 2006 | Terms of reference for EIS (
|
| 20 March 2006 |
Project deemed to not be a 'controlled action' by delegate of the Commonwealth Minister for the Environment.
|
| 14 December 2005 | Project referred to Commonwealth Minister for the Environment. |
| 4 November 2005 |
Gazettal of 'coordinated project' declaration ( |
| 19 October 2005 |
Application, including initial advice statement ( |
Airport Link project environmental impact statement documents
If you have difficulty downloading documents, please email cpdinfo@coordinatorgeneral.qld.gov.au.
- Chapter 01 - Introduction (
605 KB) - Chapter 02 - Project Rationale (
155 KB) - Chapter 03 - Project Development (
5.6 MB) - Chapter 04 - Project Description (
5.8 MB) - Chapter 05 - Traffic and Transport (
8.7 MB) - Chapter 06 - Topography Geology and Soils (
3.9 MB) - Chapter 07 - Hydrogeology and Groundwater Quality (
3.6 MB) - Chapter 08 - Surface Water Quality (
2.8 MB) - Chapter 09 - Air Quality (
14.4 MB) - Chapter 10 - Noise and Vibration (
5.4 MB) - Chapter 11 - Flora and Fauna (
4.3 MB) - Chapter 12 - Land Use and Planning (
9.3 MB) - Chapter 13 - Cultural Heritage (
1.5 MB) - Chapter 14 - Social Environment (
1.3 MB) - Chapter 15 - Urban Design (
15.4 MB) - Chapter 16 - Economics (
225 KB) - Chapter 17 - Hazard and Risk (
106 KB) - Chapter 18 - Waste Management (
78 KB) - Chapter 19 - EMP (
312 KB) - Chapter 20 - Urban Regeneration (
2.3 MB) - Chapter 21 - Cumulative Impacts (
229 KB) - Chapter 22 - Conclusions and Recommendations (
113 KB) - Chapter 23 - Glossary (
63 KB) - Chapter 24 - References (
54 KB) - Chapter 25 - Study Team (
64 KB) - Appendix A - Terms of Reference (
3.1 MB) - Appendix B - Consultation Report (
3.2 MB)
- Concept Design Drawing 01 (
84 KB) - Concept Design Drawing 02 (
81 KB) - Concept Design Drawing 03 (
109 KB) - Concept Design Drawing 04 (
95 KB) - Concept Design Drawing 05 (
605 KB) - Concept Design Drawing 06 (
577 KB) - Concept Design Drawing 07 (
614 KB) - Concept Design Drawing 08 (
556 KB) - Concept Design Drawing 09 (
599 KB) - Concept Design Drawing 10 (
378 KB) - Concept Design Drawing 11 (
636 KB) - Concept Design Drawing 12 (
391 KB) - Concept Design Drawing 13 (
620 KB) - Concept Design Drawing 14 (
385 KB) - Concept Design Drawing 15 (
382 KB) - Concept Design Drawing 16 (
607 KB) - Concept Design Drawing 17 (
632 KB) - Concept Design Drawing 18 (
536 KB) - Concept Design Drawing 19 (
354 KB) - Concept Design Drawing 20 (
554 KB) - Concept Design Drawing 21 (
589 KB) - Concept Design Drawing 22 (
552 KB) - Concept Design Drawing 23 (
536 KB) - Concept Design Drawing 24 (
739 KB) - Concept Design Drawing 25 (
560 KB) - Concept Design Drawing 26 (
525 KB) - Concept Design Drawing 27 (
555 KB) - Concept Design Drawing 28 (
454 KB) - Concept Design Drawing 29 (
450 KB) - Concept Design Drawing 30 (
552 KB) - Concept Design Drawing 31 (
437 KB) - Concept Design Drawing 32 (
610 KB) - Concept Design Drawing 33 (
380 KB) - Concept Design Drawing 34 (
388 KB) - Concept Design Drawing 35 (
357 KB) - Concept Design Drawing 36 (
406 KB) - Concept Design Drawing 37 (
380 KB) - Concept Design Drawing 38 (
276 KB) - Concept Design Drawing 39 (
164 KB) - Concept Design Drawing 40 (
107 KB) - Concept Design Drawing 41 (
116 KB) - Concept Design Drawing 42 (
101 KB) - Concept Design Drawing 43 (
159 KB) - Concept Design Drawing 44 (
142 KB) - Concept Design Drawing 45 (
111 KB) - Concept Design Drawing 46 (
128 KB) - Concept Design Drawing 47 (
125 KB) - Concept Design Drawing 48 (
80 KB) - Concept Design Drawing 49 (
128 KB) - Concept Design Drawing 50 (
112 KB) - Concept Design Drawing 51 (
136 KB) - Concept Design Drawing 52 (
142 KB) - Concept Design Drawing 53 (
79 KB) - Concept Design Drawing 54 (
119 KB) - Concept Design Drawing 55 (
117 KB) - Concept Design Drawing 56 (
115 KB) - Concept Design Drawing 57 (
104 KB) - Concept Design Drawing 58 (
103 KB) - Concept Design Drawing 59 (
89 KB) - Concept Design Drawing 60 (
117 KB) - Concept Design Drawing 61 (
79 KB) - Concept Design Drawing 62 (
120 KB) - Concept Design Drawing 63 (
69 KB) - Concept Design Drawing 64 (
110 KB) - Concept Design Drawing 65 (
115 KB) - Concept Design Drawing 66 (
78 KB) - Concept Design Drawing 67 (
102 KB) - Concept Design Drawing 68 (
89 KB) - Concept Design Drawing 69 (
217 KB) - Concept Design Drawing 70 (
114 KB) - Concept Design Drawing 71 (
105 KB) - Concept Design Drawing 72 (
99 KB) - Concept Design Drawing 73 (
107 KB) - Concept Design Drawing 74 (
130 KB) - Concept Design Drawing 75 (
105 KB) - Concept Design Drawing 76 (
88 KB) - Concept Design Drawing 77 (
143 KB) - Concept Design Drawing 78 (
83 KB) - Concept Design Drawing 79 (
95 KB) - Concept Design Drawing 80 (
102 KB) - Concept Design Drawing 81 (
84 KB) - Concept Design Drawing 82 (
77 KB) - Concept Design Drawing 83 (
80 KB) - Concept Design Drawing 84 (
106 KB) - Concept Design Drawing 85 (
92 KB) - Concept Design Drawing 86 (
93 KB) - Concept Design Drawing 87 (
88 KB)
- Chapter 01 - Traffic and Transport (
16.1 MB) - Chapter 02 - Groundwater (
12.1 MB) - Chapter 03 - Contaminated Land (
10.5 MB) - Chapter 04 - Surface Water Quality (
462 KB) - Chapter 05a - Air Quality (
8.8 MB) - Chapter 05b - Health (
2.4 MB) - Chapter 06 - Noise and Vibration (
15.8 MB) - Chapter 07 - Ecology (
4.7 MB) - Chapter 08 - Flooding (
6.2 MB) - Chapter 09 - Land Use and Planning (
7.1 MB) - Chapter 10a - Cultural Heritage (Archaeo) (
5.0 MB) - Chapter 10b - Cultural Heritage (UQ) (
121 KB) - Chapter 11 - Social Environment (
4.8 MB) - Chapter 12 - Urban Design (
11.1 MB) - Chapter 13 - Economics (
2.4 MB) - Chapter 14 - Community Consultation (
12.8 MB) - Chapter 15 - AirportLink InBrief (
4.3 MB)
- Executive Summary (
4.3 MB)
Project changes
Since the publication of the Coordinator-General's report on the EIS, the proponent has applied for the following changes to the Airport Link Project.
| Date | Activity |
|---|---|
| 31 January 2014 | Coordinator-General's report on project change ( |
| 21 January 2014 | Proponent's project change application ( |
| Date | Activity |
|---|---|
| 29 October 2009 | Coordinator-General's report on project change ( |
| 19 August 2009 | Proponent's response to submissions ( |
| 19 July 2009 to 24 July 2008 | Project change application public consultation. |
| 20 July 2009 | Independent engineering report – GM Peck and Associates ( |
| 17 June 2009 | Proponent's project change application (
|
| Date | Activity |
|---|---|
| 29 July 2008 | Coordinator-General's report on project change (
|
| 21 July 2008 | Proponent's response to submissions ( |
| 29 May 2008 to 31 May 2008 | Project change application public consultation. |
| 28 May 2008 | Proponent's project change application ( |
Change of jurisdiction
Previously, the former Environment Protection Agency was solely responsible for the regulation of Condition 20 (Appendix 1, Schedule 3) of the Coordinator-General's July 2008 change report.
Condition 20 concerns noise generated during the project's operational phase.
Following legislative amendments, this responsibility has been split as follows:
| Source of noise | Regulatory agency |
|---|---|
| State-controlled roads | Department of Transport and Main Roads |
| Local roads | Brisbane City Council |
| Non-road noise | Department of Environment and Heritage Protection |