Cross River Rail Project

Status

Approved with conditions

Jobs

1,547 (construction) + 576 (operational)

Investment

$5.4 billion

Project overview*

Project statusApproved with conditions
Description A new north-south rail line connecting Dutton Park to Bowen Hills under the Brisbane River and CBD.
Proponent Cross River Rail Delivery Authority
Location/s The rail line will run from Dutton Park to Bowen Hills through Brisbane's CBD. Map
Local government/s Brisbane City Council
Investment $5.4 billion
Key features
  • 10.2 kilometres of rail line between Dutton Park and Bowen Hills
  • 5.9 kilometres of tunnel under the Brisbane River and CBD
  • new stations at Boggo Road, Woolloongabba, Albert Street, Roma Street and Exhibition showgrounds.
Jobs
  • 1547 construction
  • 576 operational

* Project information supplied by proponent and subject to change.

Project changes

Since the publication of the Coordinator-General's report on the EIS in 2012, the proponent has applied for various changes to the Cross River Rail project.

The current project-wide conditions and recommendations, general arrangement and property impact drawings are listed below, followed by the full details of each project change.

Cross River Rail: project-wide imposed conditions and recommendations ( 675.9 KB)

This document stipulates the environmental criteria the project must achieve during construction and commissioning. Amendments to the document are made from time to time to incorporate any changes to project wide conditions or recommendations evaluated and approved by a Coordinator-General Change Report.

The document was last updated on 7 March 2025 to incorporate amendments to conditions through Change Report No.15. Details of all previous requests for project changes (including amendments to conditions and recommendations) are provided within Coordinator-General Change Reports available below.

In accordance with Imposed Condition 1, the project must be carried out generally in accordance with the below listed general arrangement and property impact drawings. Plans and drawings are amended from time to time and are subject to the scope and findings of a Coordinator-General Change Report being released for the project.

Drawing index and locality plans:

General arrangement drawings:

General construction site plans:

Long section drawings:

Property impact drawings:

Station drawings

Tunnel and portal drawings

DateActivity
7 March 2025Coordinator General's report on project change (Adobe PDF Icon 0.4 MB) released.
7 March 2025The Coordinator-General decided not to publicly notify the proponent’s change application.
6 March 2025

Proponent’s request for project change application (Adobe PDF Icon 945 KB) submitted.

DateActivity
10 July 2024 Coordinator General's report on project change ( 633.3 KB) released.
28 June 2024 Proponent submitted additional information:
29 April 2024 - 13 May 2024

Public consultation of project change application.

Volume 1 – Application (PDF icon 1.6 MB)

Volume 2 – Design Drawings (PDF icon 7.5 MB)

Volume 3 – Technical Reports (PDF icon 10 MB)

9 April 2024 Proponent’s request for project change application submitted.

DateActivity
14  March 2022 Coordinator-General's report on project change (PDF icon 0.6 MB) released.
7 March 2022 The Coordinator-General decided not to publicly notify the proponent’s change application. 
28 February 2022 Proponent’s request for project change application (PDF icon 210 KB) submitted.

DateActivity
2 February 2022 Coordinator-General's report on project change (PDF icon 0.4 MB) released.
20 January 2022 The Coordinator-General decided not to publicly notify the proponent’s change application. 
26 November 2022 Proponent submitted amended change application (PDF icon 800 MB).
28 September 2021 Proponent submitted additional information (PDF icon 1 MB).
26 August 2021 Proponent’s request for project change application (PDF icon 904 KB) submitted.

DateActivity
23 July 2021 Coordinator-General's report on project change (PDF icon 936 KB) released.
15 July 2021

Proponent submitted additional information:

10 May 2021 to 4 June 2021

Public consultation of project change application.

Volume 1 – Request for project change 11 application (PDF icon 1.8 MB)

Volume 2 – Cross River Rail Design Drawings:

Amended drawings:

*Please note, all other plans and drawings are unchanged and located above at ‘Current general arrangement and property impact drawings’.

Volume 3 – Technical Reports (PDF icon 26.1 MB)

23 April 2021 Proponent’s request for project change application submitted.

DateActivity
9 June 2021 Coordinator-General's report on project change (PDF icon 936 KB) released.
19 May 2021

Proponent submitted additional information:

23 March 2021 The Coordinator-General decided not to publicly notify the proponent’s change application.
2 March 2021

Proponent’s request for project change application submitted.

DateActivity
7 April 2021 Coordinator-General's report on project change (Adobe PDF Icon 1.5 MB) released, approving the change.
19 March 2021

Proponent submitted additional information:

28 November 2020 to 24 December 2020

Public consultation of project change application

Volume 1 – Request for project change 9 application (Adobe PDF Icon 7.5 MB)

Volume 2 – Cross River Rail Design Drawings:

Amended drawings:

Note the following drawings/plans are referenced in the application but do not include any proposed changes:

Drawing index and locality plans:

General arrangement drawings:

General construction site plans:

Long section drawings

Property impact drawings:

Station drawings

Tunnel and portal drawings

Volume 3 - technical reports

20 November 2020 Proponent’s request for project change application submitted.

DateActivity
21 December 2020 Coordinator-General’s amendment report released, correcting clerical errors identified in the change report dated 19 November 2020.
19 November 2020 Coordinator-General's report on project change released, approving the change (as amended 21 December 2020).
2 November 2020

Proponent submitted additional information:

5 September 2020 to 2 October 2020

Public consultation of project change application

Volume 1 – Request for project change 8 application

Volume 2 – Cross River Rail Design Drawings:

Drawing index and locality plans:

General arrangement drawings:

General construction site plans:

Long section drawings

Property impact drawings:

Station drawings

Tunnel and portal drawings

Volume 3 - technical reports

18 August 2020 Proponent’s request for project change application submitted.

DateActivity
16 July 2020 Coordinator-General’s report on project change (PDF icon2.6 MB) released, approving the change
4 June 2020 to 25 June 2020

Public consultation of project change application.

Volume 1 – Request for project change 7 application (PDF icon851 KB)

Volume 2 – Cross River Rail Design Drawings:

Drawing index and locality plans

General arrangement drawings:

General construction site plans:

Long section drawings (PDF icon3.3 MB)

Property impact drawings:

Station drawings (PDF icon9.1 MB)

Tunnel and portal drawings (PDF icon23 MB)

Volume 3 – Technical Reports (PDF icon1.4 MB)

Response to pre-lodgement information request (PDF icon4.7 MB)

Construction Environmental Management Plan enabling and advanced works (PDF icon7.9 MB)

21 May 2020

Proponent’s change application submitted.

DateActivity
5 June 2020

The Coordinator-General advised the proponent that Imposed Condition 10A ceases to have effect.

7 May 2020

Coordinator-General's report on project change (PDF icon462 KB) released, approving the change.

7 May 2020

The Coordinator-General decided not to publicly notify the proponent’s change application.

29 April 2020

Proponent’s change application submitted (PDF icon 215 KB).

DateActivity
4 October 2019

Coordinator-General's report on project change (PDF icon1.6 MB) released, approving the change.

3 October 2019

The Coordinator-General decided not to publicly notify the proponent’s change application.

23 September 2019

Proponent’s change application submitted (PDF icon 899 KB).

DateActivity
26 June 2019 Coordinator-General’s report on project change (PDF icon 2 MB) released, approving the change
21 June 2019

Proponent submitted additional information:

20 May 2019 to 14 June 2019

Public consultation of project change application.

Volume 1 - Request for project change 4 application (PDF icon40 MB)

Volume 2 - Design drawings:

Drawing index and locality plans

General arrangement drawings:

Long section drawings (PDF icon3 MB)

Station drawings (PDF icon7 MB)

Tunnel and portal drawings (PDF icon23 MB)

Property impact drawings:

General construction site plan drawings:

Volume 3 - Technical reports (86 MB)

1 May 2019 Proponent's change application submitted.

DateActivity
14 March 2019

Coordinator-General's report on project change (PDF icon 1.6 MB) released, approving the change.

4 March 2019

Proponent submitted revised information:

Roma Street demolition works updated traffic assessment technical note (PDF icon 15 MB)

1 December 2018 to 21 December 2018

Public consultation of project change application.

19 November 2018

Proponent's change application submitted.

DateActivity
31 August 2018 Coordinator-General's report on project change (PDF icon 824 KB) released, approving the change.
23 August 2018

Proponent submitted revised information:

3 August 2018

Proponent submitted revised information:

17 July 2018

The Coordinator-General decided not to publicly notify the proponent's change application.

28 June 2018

Proponent's change application submitted:

DateActivity
9 June 2017 Coordinator-General's report on project change (PDF icon 1.5 MB) released, approving the change.
3 April 2017 to 21 April 2017

Extension to public consultation on project change application.

Amended Volume 3 – Cross River Rail design diagrams – All documents not listed here that were subject to consultation over the period 25 February 2017 and 27 March 2017 remain unaltered:

31 March 2017 Coordinator-General decided to extend the public consultation period.
25 February 2017 to
27 March 2017

Public consultation on project change application.

Volume 1 – Request for project change (PDF icon 34.4 MB)

Volume 2 – Draft outline environmental management plan (PDF icon 3 MB)

Volume 3 – Cross River Rail design drawings – sections

Volume 4 – Technical reports (PDF icon 28.6 MB)

5 December 2016 Proponent's change application submitted.

Construction enquiries

The Cross River Rail Project is now under construction. If you have any enquiries regarding the construction of the project, contact the Cross River Rail Delivery Authority:

Environmental impact statement (EIS) process

DateActivity
26 June 2019 The Coordinator-General stated a new lapse date for the Coordinator-General’s EIS evaluation report of 31 December 2024.
8 June 2017 The Coordinator-General stated a new lapse date for the Coordinator-General’s EIS evaluation report of 9 June 2020.
13 December 2016 The Coordinator-General stated a new lapse date for the Coordinator-General's EIS Evaluation Report of 20 December 2017.
20 December 2012 Coordinator-General's report on EIS (1.85 MB) released.
4 July 2012 Supplementary information to EIS (10.69 MB) released to agencies for comment from 4 July 2012 to 1 August 2012 (and submitters for information only).
30 August 2011 to
21 October 2011
Public consultation on EIS.
19 August 2010 Terms of reference for EIS (388 KB) released.
28 July 2010 Project not deemed a 'controlled action' - provided the project is undertaken in a 'particular manner'.
10 April 2010 to
17 May 2010
Public consultation on draft terms of reference for EIS.
7 April 2010 Project referred to Commonwealth Minister for the Environment.
26 March 2010 Gazettal of 'significant project' declaration (198 KB)
26 February 2010 Application, including initial advice statement (368 KB), submitted.

Read more about the EIS process.