Project overview*
| EIS status | Approved with conditions |
| Description | A five-kilometre-long underground motorway between Brisbane's western and inner-northern suburbs. |
| Proponent | Brisbane City Council |
| Location/s | The motorway will link the Western Freeway, adjacent to the Brisbane Botanic Gardens at Toowong, with the Inner City Bypass at Kelvin Grove. Map |
| Local government/s | Brisbane City Council |
| Key features |
|
* Project information supplied by proponent and subject to change.
Environmental impact statement (EIS) process
| Date | Activity |
|---|---|
| 23 April 2010 | Coordinator-General's report on EIS (
|
| 2 July 2009 | Supplementary EIS submitted. |
|
25 October 2008 to 15 December 2008 | Public consultation on EIS. |
| 18 April 2008 | Terms of reference for EIS ( |
|
1 December 2007 to 31 January 2008 | Public consultation on draft terms of reference for EIS. |
| 30 November 2007 |
Project not deemed a controlled action by Commonwealth Minister for the Environment.
|
| 5 November 2007 | Project referred to Commonwealth Minister for the Environment. |
| 2 November 2007 |
Gazettal of significant project declaration ( |
| 28 September 2007 |
Application, including initial advice statement ( |
Project changes
| Date | Activity |
|---|---|
| 13 May 2015 | Coordinator-General's report on project change ( |
| 23 April 2015 | Proponent's project change application ( |
| Date | Activity |
|---|---|
| 24 September 2012 | Coordinator-General's report on project change ( |
| 21 August 2012 | Proponent's project change application submitted.
|
| Date | Activity |
|---|---|
| 27 July 2012 | Coordinator-General's report on project change ( |
| 13 July 2012 | Proponent's project change application ( |
| Date | Activity |
|---|---|
| 12 January 2012 | Coordinator-General's report on project change ( |
| 7 October 2011 | Proponent's project change application ( |
| Date | Activity |
|---|---|
| 18 August 2011 | Coordinator-General's report on project change ( |
| 22 July 2011 | Proponent's project change application ( |
| Date | Activity |
|---|---|
| 18 August 2011 | Coordinator-General's report on project change ( |
| 23 June 2011 | Proponent's project change application ( |
| Date | Activity |
|---|---|
| 17 June 2011 | Coordinator-General's report on project change ( |
| 3 June 2011 | Amendment to project change application ( Attachments: |
| 25 October 2010 | Proponent's project change application ( |
| Date | Activity |
|---|---|
| 17 December 2010 | Coordinator-General's report on project change ( Documents that informed the report included:
|
|
30 October 2010 to 19 November 2010 | Public consultation on project change application. |
| 25 October 2010 | Proponent's project change application ( |
Environmental impact statement documents
- SEIS June 2009 (
7.7 MB) - Appendix A - submission analysis (
5.5 MB) - Appendix B - response to submissions (
6.9 MB) - Appendix C - community consultation report (
6.9 MB) - Appendix D - environmental management plan (
4.9 MB) - Appendix E - supplementary technical papers (
8.1 MB)
- Drawing index (
14.0 MB) - 1.01 Planning layouts - key sheets layout (
864 KB) - 1.02 Planning layout - plan 1 of 10 (
1.3 MB) - 1.03 Planning layout - plan 2 of 10 (
1.3 MB) - 1.04 Planning layout - plan 3 of 10 (
1.3 MB) - 1.05 Planning layout - plan 4 of 10 (
1.2 MB) - 1.06 Planning layout - plan 5 of 10 (
1.2 MB) - 1.07 Planning layout - plan 6 of 10 (
1.2 MB) - 1.08 Planning layout - plan 7 of 10 (
1.2 MB) - 1.09 Planning layout - plan 8 of 10 (
1.4 MB) - 1.10 Planning layout - plan 9 of 10 (
1.5 MB) - 1.11 Planning layout - plan 10 of 10 (
1.1 MB) - 2.01 Typical cross sections - two lane tunnel boring machine (
384 KB) - 2.02 Typical cross sections - two lane tunnel boring machine cross passage (
446 KB) - 2.03 Typical cross sections - two lane tunnel boring machine cross passage section (
220 KB) - 2.04 Typical cross sections - two lane and cover tunnel with ventilation tunnel (
320 KB) - 3.01 Longitudinal section - northern link tunnel eastbound sheet 1 of 2 (
506 KB) - 3.02 Longitudinal section - northern link tunnel eastbound sheet 2 of 2 (
452 KB) - 3.03 Longitudinal section - northern link tunnel westbound sheet 1 of 2 (
514 KB) - 3.04 Longitudinal section - northern link tunnel westbound sheet 2 of 2 (
482 KB) - 4.01 Construction site plan - proposed construction sites - key sheets layout (
890 KB) - 4.02 Construction site plan - indicative Western Freeway construction site (
2.4 MB) - 4.03 Construction site plans - proposed Western Freeway connection - indicative conveyor location (
2.4 MB) - 5.01 Traffic management and staging - key sheets layout (
897 KB) - 5.02 Traffic management and staging - Western Freeway connection stage 1 of 4 (
1.3 MB) - 5.03 Traffic management and staging - Western Freeway connection stage 2 of 4 (
1.3 MB) - 5.04 Traffic management and staging - Western Freeway connection stage 3 of 4 (
1.3 MB) - 5.05 Traffic management and staging - Western Freeway connection stage 4 of 4 (
1.3 MB) - 5.06 Traffic management and staging - Inner city bypass connection stage 1 of 4 (
1.0 MB) - 5.07 Traffic management and staging - Inner city bypass connection stage 2 of 4 (
1.0 MB) - 5.08 Traffic management and staging - Inner city bypass connection stage 3 of 4 (
1.0 MB) - 5.09 Traffic management and staging - Inner city bypass connection stage 4 of 4 (
1.0 MB) - 6.01 Ventilation systems - Ventilation plan - key sheets layout (
869 KB) - 6.02 Ventilation systems - Ventilation sites - Western Freeway connection (
2.0 MB) - 6.03 Ventilation systems - Ventilation sites - Inner city bypass connection (
1.6 MB) - 7.01 Estimated tunnel settlement contours - key sheet layout (
885 KB) - 7.02 Estimated tunnel settlement contours - plan 1 of 6 (
5.3 MB) - 7.03 Estimated tunnel settlement contours - plan 2 of 6 (
2.2 MB) - 7.04 Estimated tunnel settlement contours - plan 3 of 6 (
2.1 MB) - 7.05 Estimated tunnel settlement contours - plan 4 of 6 (
2.4 MB) - 7.06 Estimated tunnel settlement contours - plan 5 of 6 (
2.9 MB) - 7.07 Estimated tunnel settlement contours - plan 6 of 6 (
4.7 MB)
- Executive Summary (
15.4 MB) - Glossary of Terms (
408 KB) - References (
192 KB) - Study Team (
198 KB) - 01 Introduction (
1.7 MB) - 02 Project Rationale (
2.9 MB) - 03 Project Development (
7.4 MB) - 04 Project Description (
11.0 MB) - 05 Traffic and Transport (
13.0 MB) - 06 Geology and Soils (
3.7 MB) - 07 Hydrology (
5.7 MB) - 08 Air Quality and Greenhouse gases (
2.1 MB) - 09 Noise and Vibration (
7.0 MB) - 10 Ecology (
2.0 MB) - 11 Planning and Land Use (
6.3 MB) - 12 Cultural Heritage (
3.8 MB) - 13 Social Environment (
1.9 MB) - 14 Urban Design and Visual Environment (
13.5 MB) - 15 Economic Environment (
781 KB) - 16 Hazard and Risk (
632 KB) - 17 Waste Management (
598 KB) - 18 Health and Safety (
668 KB) - 19 Draft Outline Environmental Management Plan (
2.6 MB) - 20 Urban Regeneration (
1.7 MB) - 21 Cumulative Impacts (
1.9 MB) - 22 Conclusions (
830 KB) - Appendix A - ToR. EIS Guideline in response to ToR (
1.9 MB) - Appendix B - Community Consultation Report (
1.7 MB)
- Drawing Index (
1.1 MB) - 1.01 Planning layouts - key sheets layout (
7.9 MB) - 1.02 Planning layouts - Plan 01 of 11 (
10.2 MB) - 1.03 Planning layouts - Plan 02 of 11 (
7.8 MB) - 1.04 Planning layouts - Plan 03 of 11 (
7.8 MB) - 1.05 Planning layouts - Plan 04 of 11 (
6.6 MB) - 1.06 Planning layouts - Plan 05 of 11 (
7.5 MB) - 1.07 Planning layouts - Plan 06 of 11 (
7.2 MB) - 1.08 Planning layouts - Plan 07 of 11 (
6.8 MB) - 1.09 Planning layouts - Plan 08 of 11 (
7.3 MB) - 1.10 Planning layouts - Plan 09 of 11 (
6.9 MB) - 1.11 Planning layouts - Plan 10 of 11 (
6.7 MB) - 1.12 Planning layouts - Plan 11 of 11 (
6.2 MB) - 2.01 Typical cross section - one lane road header tunnel with longitudinal passage (
334 KB) - 2.02 Typical cross section - two lane tunnel boring machine (
509 KB) - 2.03 Typical cross section - two lane road header tunnel with longitudinal passage (
362 KB) - 2.04 Typical cross section three lane road header tunnel with longitudinal passage (
387 KB) - 2.05 Typical cross section - three lane road header tunnel at Y - Junction (
448 KB) - 2.06 Typical cross section - two lane tunnel boring machine cross passage (
430 KB) - 2.07 Typical cross section - road header cross passage (
348 KB) - 2.08 Typical cross section - cross passage (
181 KB) - 2.09 Typical cross section – structures (
342 KB) - 3.01 Longitudinal sections - Northern link tunnel eastbound sheet 1 of 2 (
765 KB) - 3.02 Longitudinal sections - Northern link tunnel eastbound sheet 2 of 2 (
652 KB) - 3.03 Longitudinal sections - Northern link tunnel westbound sheet 1 of 2 (
793 KB) - 3.04 Longitudinal sections - Northern link tunnel westbound sheet 2 of 2 (
739 KB) - 3.05 Longitudinal sections - Northern link tunnel eastbound entry ramp (
674 KB) - 3.06 Longitudinal sections - Northern link tunnel westbound exit ramp (
619 KB) - 3.07 Longitudinal sections - Northern link tunnel eastbound exit ramp (
517 KB) - 3.08 Longitudinal sections - Northern link tunnel westbound entry ramp (
568 KB) - 3.09 Longitudinal sections - Northern link tunnel eastbound entry ramp elevated structures (
547 KB) - 4.01 Proposed construction sites - key sheets layout (
8.5 MB) - 4.02 Construction site plan - proposed Western Freeway construction site plan 1 of 4 (
6.8 MB) - 4.03 Construction site plan - proposed Toowong construction site plan 2 of 4 (
5.7 MB) - 4.04 Construction site plan - proposed Kelvin Grove construction site plan 3 of 4 (
5.3 MB) - 4.05 Construction site plan - proposed Western Freeway conveyor location plan 4 of 4 (
9.6 MB) - 5.01 Traffic management and staging - key sheets layout (
7.9 MB) - 5.02 Traffic management and staging - Western Freeway connection stage 1 of 4 (
7.7 MB) - 5.03 Traffic management and staging - Western Freeway connection stage 2 of 4 (
7.2 MB) - 5.04 Traffic management and staging - Western Freeway connection stage 3 of 4 (
7.3 MB) - 5.05 Traffic management and staging - Western Freeway connection stage 4 of 4 (
7.3 MB) - 5.06 Traffic management and staging - Toowong connection stage 1 of 3 (
6.5 MB) - 5.07 Traffic management and staging - Toowong connection stage 2 of 3 (
6.5 MB) - 5.08 Traffic management and staging - Toowong connection stage 3 of 3 (
6.5 MB) - 5.09 Traffic management and staging - Kelvin Grove connection stage 1 of 3 (
6.1 MB) - 5.10 Traffic management and staging - Kelvin Grove connection stage 2 of 3 (
6.2 MB) - 5.11 Traffic management and staging - Kelvin Grove connection stage 3 of 3 (
6.2 MB) - 5.12 Traffic management and staging - Inner city bypass connection stage 1 of 4 (
5.8 MB) - 5.13 Traffic management and staging - Inner city bypass connection stage 2 of 4 (
5.8 MB) - 5.14 Traffic management and staging - Inner city bypass connection stage 3 of 4 (
5.8 MB) - 5.15 Traffic management and staging - Inner city bypass connection stage 4 of 4 (
5.9 MB) - 6.01 Ventilation site - key sheets layout (
7.9 MB) - 6.02 Ventilation site - Western Freeway connection plan 1 of 2 (
3.1 MB) - 6.03 Ventilation site - Inner city bypass connection plan 2 of 2 (
2.8 MB) - 7.01 Estimated tunnel settlement contours - key sheet layout (
8.0 MB) - 7.02 Estimated tunnel settlement contours - plan 1 of 7 (
15.1 MB) - 7.03 Estimated tunnel settlement contours - plan 2 of 7 (
9.5 MB) - 7.04 Estimated tunnel settlement contours - plan 3 of 7 (
8.0 MB) - 7.05 Estimated tunnel settlement contours - plan 4 of 7 (
9.8 MB) - 7.06 Estimated tunnel settlement contours - plan 5 of 7 (
11.9 MB) - 7.07 Estimated tunnel settlement contours - plan 6 of 7 (
9.4 MB) - 7.08 Estimated tunnel settlement contours - plan 7 of 7 (
10.1 MB)
- 01 Traffic and Transport (
34.6 MB) - 02 Geology and Soils (
10.9 MB) - 03 Contaminated Land (
15.5 MB) - 04 Groundwater (
13.9 MB) - 05 Surface Water (
4.3 MB) - 06 Flooding (
9.6 MB) - 07 Air Quality (Operation) (
8.3 MB) - 07a Air Quality (Construction) (
11.6 MB) - 07b Air Quality (Green House Gases) (
291 KB) - 08 Air Quality (Health) (
1.4 MB) - 09a Noise and Vibes (Construction) (
11.1 MB) - 09b Noise and Vibes (Operation) (
13.9 MB) - 10 Ecology (
5.6 MB) - 11 Land Use (
9.0 MB) - 12 Cultural Heritage (
10.4 MB) - 13 Social Environment (
7.2 MB) - 14 Urban Design (
8.9 MB) - 15 Economics (
857 KB)
Issues or concerns
As part of the Coordinator-General's conditions of approval for the project, the Brisbane City Council has appointed an independent community liaison representative to:
- act as an independent community representative, assisting the community consultation process, including chairing the community liaison group meetings
- be directly available to the community
- resolve community complaints not resolved by the project's complaints process.
If you have any issues or concerns you would like to report, contact Transcity:
- 24-hour community hotline (freecall): 1800 778 772
- Email: info@transcityjv.com.au
Please advise Transcity what you require, e.g. a response, feedback, apology, etc.
If Transcity does not respond to or resolve your issues or concerns satisfactorily, contact the independent community liaison representative:
- Freecall:1800 769 279
- Email: LegacyWayICLR@brisbane.qld.gov.au
- Visit: Legacy Way Visitors' Centre
Level 1, 80 Jephson Street, Toowong
Monday to Friday, between 9am to 4pm (by appointment)