Port of Gladstone Gatcombe and Golding Cutting Channel Duplication Project

Status

Approved with conditions

Jobs

386 (construction) + 23 (operational)

Investment

$760 million

Project overview*

EIS statusApproved with conditions
Description Duplication of the existing Gatcombe and Golding Cutting shipping channels to allow for improved two-way passage by deepening and widening the existing channels. This will allow passage for larger vessels under all weather and tidal conditions.
Proponent Gladstone Ports Corporation Limited
Location/s

Port of Gladstone.

Find this and other projects on our map.

Local government/s Gladstone Regional Council
Investment $760 million
Key features
  • dredging works to deepen and widen the existing channels to a depth of approximately 16.1 m, a width of 200 m and a total length of approximately 15 km
  • dredging a total of 12.85 million cubic metres
  • capital dredged material would be beneficially reused to create reclamation areas for potential future port infrastructure.
Jobs
  • 386 full time equivalent (FTE) jobs (construction)
  • 23 FTE jobs (operational)

* Project information supplied by proponent and subject to change.

Environmental impact statement (EIS) process

DateActivity
6 July 2026 The Coordinator-General stated a new lapse date for the Coordinator-General’s EIS evaluation report of 8 July 2036.
6 July 2026 Clerical amendment  to the Coordinator-General’s report on final EIS.
24 December 2020 Australian Government Minister for the Environment’s approval of 'controlled action', subject to conditions.
8 July 2020 Coordinator-General’s report on the final EIS (PDF icon 9.8 MB) released
30 September 2019 The Coordinator-General accepted the draft EIS as the final EIS.
25 September 2019 The proponent lodged a revised draft EIS.
12 August to 30 August 2019 Targeted consultation on the preliminary revised draft EIS with other government agencies.
9 July 2019 Additional information to the EIS requested by the Coordinator-General.
8 April 2019 to 23 May 2019 Draft EIS public consultation:
26 September 2018 Coordinator-General extended the project declaration lapse date to 30 September 2019.
22 September 2017 Coordinator-General extended the project declaration lapse date to 28 September 2018.
23 May 2016 Coordinator-General extended the project declaration lapse date to 30 September 2017.
2 December 2014 Coordinator-General extended the project declaration lapse date to 8 June 2016.
8 December 2012 Terms of reference for EIS ( 531.1 KB) released.
23 October 2012 Australian Government Minister for the Environment decided the project is a 'controlled action'.

A project that has the potential to have a significant impact on matters of national environmental significance is called a 'controlled action' and requires approval under the Environment Protection and Biodiversity Conservation Act 1999 (Cth).

6 October 2012 to
5 November 2012
Draft terms of reference for EIS public consultation.
26 September 2012 Project referred to Australian Government Minister for the Environment.
25 September 2012 Gazettal of 'coordinated project' declaration ( 118.4 KB)
21 September 2012 Application, including initial advice statement ( 3.3 MB), submitted.

Read more about the EIS process.

Environmental impact statement documents

If you have difficulty downloading documents, please email enquire@coordinatorgeneral.qld.gov.au.

Chapters

Appendices

Chapters

Appendices

Further information

For more information, visit the Gladstone Ports Corporation website.