Winchester South project

Status

Approved with conditions

Jobs

500 (construction) + 500 (operational)

Investment

$1 billion

Project overview*

EIS statusApproved with conditions
Description Greenfield open cut coal mine producing up to 17 million tonnes per annum (Mtpa) of primarily metallurgical run-of-mine coal (11 Mtpa product coal) used for steel making.
Proponent Whitehaven WS Pty Ltd, a wholly owned subsidiary of Whitehaven Coal
Location/s

Approximately 30 km south-east of Moranbah.

Find this and other projects on our map.

Local government/s Isaac Regional Council
Investment $1 billion
Key features
  • open-cut primarily metallurgical coal mine
  • mine infrastructure areas including workshops and a coal handling and preparation plant
  • rail loop and train load out facility connecting to the Norwich Park Branch Railway
  • private access road
  • raw water pipeline connecting to the Eungella pipeline network
  • electricity transmission line from the existing power network
Construction start date 2026
Jobs
  • 500 full time equivalent (FTE) construction jobs
  • 500 FTE operational jobs

* Project information supplied by proponent and subject to change.

Environmental impact statement (EIS) process

DateActivity
23 November 2023

Coordinator-General’s report on the EIS (pdf_file 21.6 KB) released.

Supplementary documentation provided by the proponent.

7 July 2023

The Coordinator-General accepted the draft EIS and the revised draft EIS as the final EIS.

Final EIS, including appendices.

2 May 2023 The Coordinator-General stated a new project declaration lapse date of 7 July 2023
8 February 2023 The Coordinator-General stated a new project declaration lapse date of 8 May 2023.
21 November 2022 to 19 December 2022

Revised draft EIS public consultation.

Revised draft EIS.

23 February 2022 The Coordinator-General stated a new project declaration lapse date of 6 March 2023.
3 December 2021 Additional information for the EIS requested by the Coordinator-General.
4 August 2021 to 15 September 2021 Draft EIS public consultation.
Draft EIS, including appendices.
26 February 2021 Coordinator-General stated a new project declaration lapse date of 4 March 2022.
4 September 2019 Terms of reference for an EIS (pdf_file 660 KB) released.
17 and 18 July 2019

Australian Minister for the Environment decided the project is a 'controlled action'.

More information
24 June 2019 to 19 July 2019 Public consultation period on draft terms of reference (pdf_file 1.2 MB).
17 April 2019 Gazettal (pdf_file 247 KB) of ‘coordinated project’ declaration.
14 February 2019 Application, including initial advice statement (pdf_file 8.8 MB), submitted.

Environmental Impact statement documents