Capricornia Pumped Hydroelectric Energy Storage and Transmission Project

Status

EIS active

Jobs

600 (construction) + 65 (operational)

Investment

$2.87 billion

Project overview*

EIS statusEIS active
Description Pumped hydroelectric energy storage (PHES) and transmission project with a stored capacity of up to 750 megawatts for approximately 16 hours for a 24 hour period.
Proponent

CI QLD PHES 1 Pty Ltd as trustee for CI QLD PHES 1 Trust (trading as Capricornia Pumped Hydro) and CI QLD Infrastructure 1 Pty Ltd (joint proponents).

Location/s

Approximately 80km west of Mackay and 10km northwest of Eungella.

Find this and other projects on our map.

Local government/s Isaac Regional Council and Mackay Regional Council
Investment

$2.87 billion

Key features
  • approximately 18 gigalitre upper reservoir with valley infill wall and an instream lower reservoir within Broken River, both with associated spillways
  • approximately 750 megawatt powerhouse generation facility, intakes, and tunnels for water conveyance to connect the reservoirs and powerhouse
  • approximately 18km long overhead transmission line and substation connecting to the existing Powerlink Strathmore to Nebo 275 kilovolt transmission line
  • supporting infrastructure (temporary and permanent).
Construction start date 2026
Jobs
  • 600 full time equivalent (construction)
  • 65 full time equivalent (operation)

* Project information supplied by proponent and subject to change.

Environmental impact statement (EIS) process

DateActivity
Currently Draft EIS being prepared by proponent.
24  March 2026The Coordinator-General stated a new project declaration lapse date of 25 March 2027.
25 September 2024 Terms of reference for an EIS ( 1.0 MB) released.

The terms of reference includes the requirement to address matters outlined in the Preparing an EIS - Guideline for proponents (February 2024) ( 419.5 KB).
15 July to 23 August 2024

Draft terms of reference for EIS ( 1.2 MB) public consultation.

The draft terms of reference includes the requirement to address matters outlined in the Preparing an EIS - Guideline for proponents (February 2024) ( 419.5 KB).

18 April 2024 Gazettal ( 245.5 KB) of 'coordinated project' declaration.
13 December 2023

Application, including initial advice statement ( 32.2 MB) submitted.

11 December 2023 Australian Minister for the Environment and Water decided the PHES component is a ‘controlled action’. 

A project that has the potential to have a significant impact on matters of national environmental significance is called a 'controlled action' and requires approval under the Environment Protection and Biodiversity Conservation Act 1999 (Cth).

7 December 2023 Australian Minister for the Environment and Water decided the transmission component is a ‘controlled action’.  

A project that has the potential to have a significant impact on matters of national environmental significance is called a 'controlled action' and requires approval under the Environment Protection and Biodiversity Conservation Act 1999 (Cth).

Further Information

Read more about the EIS process.