Kidston Pumped Storage Hydro Project

A 250-megawatt pumped storage hydroelectric power generation facility.

Status

Under construction

Jobs

370 (construction) + 9 (operational)

Investment

$777 million

About the project

The Kidston Pumped Storage Hydro project is a 250-megawatt pumped storage hydroelectric power generation facility located within the decommissioned Kidston gold mine in North Queensland. Designed to generate, store and dispatch renewable energy on demand during peak periods, the projects includes the following components:

  • an upper reservoir formed by a 20-metre-high dam around the existing Wises Pit
  • a lower reservoir utilising the existing Eldridge Pit
  • a powerhouse cavern with the capacity to generate 250 megawatts
  • a tailrace allowing water to pass from the powerhouse to the reservoirs
  • a spillway from the upper reservoir to the Copperfield River.
Proponent Genex Power Limited
Location

Kidston, Queensland approximately 280 km north-west of Townsville.

Find this and other projects on our map.

Local government Etheridge Shire Council
Jobs
  • 370 (construction over three and a half years)
  • 9 (operational)
Investment $777 million
Construction start date 2021
Construction end date 2026

Latest updates

Construction commenced in April 2021.

When operational, it will generate 250 megawatts of power for up to 8 hours for North Queensland. Operation of the project will be underpinned by Energy Australia under an Energy Storage Services Agreement for up to 30 years

Environmental impact assessment process

This project has been declared a coordinated project by the Coordinator-General under the State Development and Public Works Organisation Act 1971. We play a role making sure benefits and risks are managed through a rigorous assessment process, and that approvals are coordinated across local, state and federal jurisdictions. Find out more about the coordinated project environmental impact assessment process.

Declaration date 28 September 2018
Assessment process Coordinated project requiring an impact assessment report (IAR)
Current stage IAR approved with conditions

Assessment milestones

DateActivity
27 April 2021 Coordinator-General’s report on project change (pdf_file 145 KB) released.
24 September 2019 Coordinator-General correspondence to Genex Power Limited (pdf_file 306 KB).
22 May 2019 Coordinator-General correspondence to Genex Power Limited (pdf_file 230 KB).
5 April 2019 Coordinator-General’s report on the IAR (pdf_file 2.4 MB) release.
28 March 2019

The Coordinator-General accepted the draft IAR as the final IAR. Impact assessment report (pdf_file 28 MB), submitted.

Supplementary information to the IAR (pdf_file 5.3 MB), submitted.

IAR sections, submitted:

25 March 2019 The Coordinator-General accepted the draft IAR as the final IAR. The evaluation stage has commenced.
11 January 2019 The proponent lodged a draft IAR.
28 September 2018 Gazettal (pdf_file 250 KB) of 'coordinated project' declaration.
28 September 2018 Application, including initial advice statement submitted.

Further information