About the project
The Burdekin Falls Dam was completed in 1987 and is the largest water storage asset in Queensland. The project proposes to increase the storage capacity of the existing dam by raising the spillway by two metres and raising the associated abutments and saddle dams. The project also includes adjustments to apron and splitter piers and access road realignments and upgrades.
As well as its vital role supporting the region’s agriculture, the dam supplies water to Townsville about 150 km to the north.
| Proponent | Sunwater Limited |
| Location | The project is located on the Burdekin River approximately 160 kilometres upstream from the river’s mouth and approximately 210km south of Townsville. |
| Local government |
|
| Jobs | 350 (peak construction) |
| Investment | Initial investment (2018) of up to $502 million. The 2024-2025 Queensland Budget confirmed funding of $540 million will remain allocated to improving and raising Burdekin Falls Dam by two metres. This $540 million commitment includes $100 million originally allocated for the project and $440 million allocated through the 2023-2024 Queensland Budget. |
Environmental impact assessment process
This project has been declared a coordinated project by the Coordinator-General under the State Development and Public Works Organisation Act 1971. We play a role making sure benefits and risks are managed through a rigorous assessment process, and that approvals are coordinated across local, state and federal jurisdictions. Find out more about the coordinated project environmental impact assessment process.
| Declaration date | 29 July 2020 |
| Assessment process | Coordinated project requiring an environmental impact statement (EIS) Bilateral assessment for a controlled action under the Environment Protection and Biodiversity Conservation Act 1999. |
| Current stage | The draft EIS is being prepared by proponent. |
| Declaration lapse date | 7 April 2027 |
Assessment milestones
| Date | Activity |
|---|---|
| 24 March 2025 | Coordinator-General stated a new project declaration lapse date of 7 April 2027. |
| 12 September 2023 | Coordinator-General stated a new project declaration lapse date of 7 April 2025. |
| 12 December 2022 | Proponent confirmed a refined scope of works, raising to two metres. |
| 23 August 2022 | Coordinator-General stated a new project declaration lapse date of 3 October 2023. |
| 1 April 2021 | Terms of reference for an EIS ( |
| 30 November 2020 to 29 January 2021 | Public consultation on the draft terms of reference for EIS ( |
| 28 August 2020 | Australian Minister for the Environment decided that the project is a ‘controlled action'. |
| 29 July 2020 | Gazettal ( |
| 11 June 2020 |
Application, including initial advice statement ( |
Further information
- Find out what it means to have a project declared ‘coordinated’ – with details of the process, the benefits and what kinds of projects can potentially be declared.
- Explore other coordinated projects.