About the project
Proposal to develop a pumped hydro electricity generation facility involving construction of an upper reservoir and repurposing the mine pit created by the existing Mount Rawdon Mine for the lower reservoir. The project involves:
- a generation facility, comprising a lower storage (formed by the decommissioned mine pit), upper storage (formed by a purpose-built valley fill dam), waterway tunnels linking the two storages, underground power station, switchyard and associated access works
- an electricity transmission line and substation, connecting the generation facility to the existing Powerlink transmission network
- upgrades/duplication of the existing water pipeline (connecting the generation facility to Paradise Dam), comprising a pump, pipes and power supply to enable the first fill of the generation facility
| Proponent | Mt Rawdon Pumped Hydro Pty Ltd |
| Location | Approximately 75 km south-west of Bundaberg. |
| Local government | North Burnett Regional Council and Bundaberg Regional Council |
| Key features |
|
Environmental impact assessment process
This project has been declared a coordinated project by the Coordinator-General under the State Development and Public Works Organisation Act 1971. We play a role making sure benefits and risks are managed through a rigorous assessment process, and that approvals are coordinated across local, state and federal jurisdictions. Find out more about the coordinated project environmental impact assessment process.
Declaration date | 11 October 2022 |
Assessment process | Coordinated project requiring an environmental impact statement (EIS) Bilateral assessment for a controlled action under the Environment Protection and Biodiversity Conservation Act 1999. |
Current stage | The draft EIS being prepared by the proponent |
Declaration lapse date | 16 December 2028 |
Assessment milestones
| Date | Activity |
|---|---|
| Currently | Draft EIS being prepared by proponent. |
| 23 October 2026 | Coordinator-General stated a new project declaration lapse date of 16 December 2028. |
| 5 December 2024 | Coordinator-General stated a new project declaration lapse date of 16 December 2026. |
| 16 June 2023 | Terms of reference for EIS ( |
| 4 March 2023 to 11 April 2023 | Draft terms of reference ( |
| 16 November 2022 | Australian Minister for the Environment and Water decided the pumped hydropower energy storage component of the project is a ‘controlled action’. |
| 11 October 2022 | Gazettal ( |
| 27 September 2022 | Australian Minister for the Environment and Water decided the transmission line component of the project is a ‘controlled action’. |
| 27 June 2022 |
Application, including Initial advice statement ( |