Paradise Dam Improvement Project
Status
Impact assessment report (IAR) active
Jobs
Median construction workforce of 600 (with a peak of 750 workers).
Investment
$4.4 billion
Project overview*
| EIS status | Impact assessment report (IAR) active |
| Description | Proposal to construct a replacement dam wall to restore Paradise Dam to its original capacity and full supply level, reinstate water supplies to the existing market and provide water security to the Bundaberg and Burnett regions for decades to come. |
| Proponent | Sunwater Limited |
| Location/s | The project is located on the Burnett River, approximately 20km northwest of Biggenden and 80km south-west of Bundaberg. |
| Local government/s |
|
| Investment | $4.4 billion |
| Key features |
|
| Construction start date | 2028 (subject to approvals) |
| Jobs |
|
* Project information supplied by proponent and subject to change.
Impact assessment report (IAR) process
| Date | Activity |
|---|---|
| Currently | Draft IAR being prepared by proponent. |
| 26 March 2026 | Guideline for the Impact Assessment Report ( |
| 8 August 2025 |
Australian Government Minister for the Environment and Water decided the project is a 'controlled action'.
A project that has the potential to have a significant impact on matters of national environmental significance is called a 'controlled action' and requires approval under the Environment Protection and Biodiversity Conservation Act 1999 (Cth). |
| 8 August 2025 | Gazettal ( |
| 2 July 2025 |
Application, including initial advice statement ( |
| 27 June 2025 | Project referred to the Australian Government Minister of the Environment and Water. |
Further information
Last updated: 26 March 2026